IMPROVEMENT IN PERFORMANCE OF COOLING TOWER OF THERMAL POWER PLANT

Authors

  • Prof. Dhaval P Patel Mechanical Engineering Department, Gandhinagar Institute of Technology, dhaval.patel@git.org.in
  • Prof. N R Sheth Mechanical Engineering Department, Government Engineering College, Valsad
  • Ankit Patel P G Student, Mechanical Engineering Department, Government Engineering College, Valsad,

Keywords:

Power generating plant, cooling tower, first law analysis, effectiveness and characteristic of cooling tower.

Abstract

The first law analysis of the coal fired thermal power station namely
Gandhinagar Thermal Power Station (GTPS).In research paper, a detailed energy study is
shown for 210MW, of coal fired thermal power plant at Gandhinagar Thermal Power Station
(GTPS) to evaluate the plant and subsystem [feed water heaters (high pressure and low
pressure)],etc. efficiencies. Research represent cooling tower effectiveness of thermal power
and gives suggestion for improvement of cooling tower performance.